• Project ObjectivesEnable the introduction of double deck deliveries direct to over 200 retail sites
  • Project ObjectivesInstall double deck lifts at 150 Extra & Superstores across UK
  • Project DesignSites surveys at all stores/ Autoturn® to ensure vehicle accessibility
  • Project Design6.5-tonne double deck & V2G lifts/ Loadhouse sealed to store
  • Project DesignBespoke dock extensions; wheel ramps; low canopies; steep ramps
  • Project FulfilmentExisting loading equipment stripped out & (if possible) refurbished & recycled
  • Project FulfilmentCrane install 3 hours – to avoid disrupting deliveries
  • Project FulfilmentEach lift loadhouse installed & commissioned in 1.5 days
  • “The job was completed quickly and to a high standard...and I can still accept deliveries from single deck vehicles”